What’s is a Critical path?
·
Sets out all the individual
activities that make up a larger project.
·
Shows the order in which activities
have to be undertaken.
·
Shows which activities can only take
place once other activities have been completed.
·
Shows which activities can be
undertaken reducing the overall time taken to complete the whole project.
·
Shows when certain resources will be
needed for example, a crane to be hired for a building site.
The critical path refers to the way
the diagram shows those activities that must be completed, and complete in a
specific order, so that the project can be completed successfully and on time. Each
circle represents an activity that needs to be completed and each line shows
the relationship between two activities. The critical path will be the longest
path through the diagram, and will show how long a project is expected to take
if the scope does not change and everything goes according to plan.